Skip to content

Yukon's melting snow brings risk to site of last year's mine disaster

WHITEHORSE — Crews in Yukon are working to prepare for an influx of extra water as snow melts at the site of last year's disaster at the Eagle Gold mine.
8926547d93b9d70c979eb86ba378fb1a66b8436e00b02c0d87047c71f5122051
Victoria Gold's Eagle gold mine site north of Mayo, Y.T., is shown in this handout aerial photo taken Wednesday, July 3, 2024. THE CANADIAN PRESS/HO — Yukon Government

WHITEHORSE — Crews in Yukon are working to prepare for an influx of extra water as snow melts at the site of last year's disaster at the Eagle Gold mine.

An update from the territorial government says the main risk as temperatures warm is that snow and ice melts faster than water can be treated or stored, leading to the possibility of an uncontrolled release of water containing cyanide.

The update says the receiver and contractors on the site, about 480 kilometres north of Whitehorse, are building sumps, ditches and pipelines to divert melt water away from water that contains cyanide and areas impacted by cyanide.

The Eagle Gold mine was the site of a disaster on June 24, 2024, after a heap leach containment facility failed, dumping millions of tonnes of cyanide-soak ore into the environment.

The update says snowpack is "average" at the mine site and weather in the coming weeks will play a significant role in the speed of melt.

The government statement says two additional storage ponds are also being built to help hold water containing cyanide until it can be treated, with one expected to be completed "soon" and a second expected to be finished in May.

The statement says the ponds will provide more than 200,000 cubic metres of additional storage space — roughly 80 Olympic-sized swimming pools.

This report by The Canadian Press was first published April 17, 2025.

The Canadian Press